Phase 2A – Completed December 2021
Phase 2B – Completed August 2023

The second phase of the restoration of Assumption Church will be divided into three parts, A, B, and C.

Phase 2 requires that the plaster in the ceiling be consolidated to ensure its adherence to the lathes. This work involves applying a compound from inside the attic. The insulation is removed from the attic to expose the lathe and plaster above the ceiling.

Any loose plaster is vacuumed out of the space between the lathe. Several applications of this compound are required.

At the same time, scaffolding is required to ensure that any compound that may penetrate the exposed surface is removed immediately.

Once completed, plaster repairs will be made and painting will take place.

Work will also take place to update the electrical, fire systems, lighting and catwalk in the attic.

Work to Date: